Updates

The project is under construction.

Friday, April 30, 2021

Over the coming weeks, construction activities will take place in the following areas:

  • Cherry Creek State Park.
    • Construction in Cherry Creek State Park will resume this summer and continue through the end of the year.
    • Construction near the Cottonwood Creek Trail has been completed, and the trail is open for use.
    • Restoration in the Park along Peoria Street will take place through spring.
  • Near the intersection of Havana Street and Berry Avenue. Restoration activities will take place in the coming weeks. Additional construction will take place at this location later this year.
  • Village Greens Park east of Cherry Creek Village North. Restoration of the ballfields is ongoing with the ballfields expected to reopen in May. Please note that restoration is weather dependent.
  • Near Hampden Avenue between Akron and Yosemite streets. Crews continue to work at the regulator station near this location. Work will continue into summer 2021.

Please stay clear of work areas for your safety and the safety of our crews. Please note that construction schedules are subject to change.

Click here to view a map of the current and upcoming work areas.


Friday, April 16, 2021

Over the coming weeks, construction activities will take place in the following areas:

  • Cherry Creek State Park.
    • Crews have completed natural gas line installation activities along Peoria Street. Construction in the Park will resume this summer and continue through the end of the year.
    • Crews are restoring the Cottonwood Creek Trail with the trail expected to reopen this month. View a map of the trail closure.
    • Restoration of work areas along Peoria Street will take place through spring.
  • Village Greens Park east of Cherry Creek Village North. Restoration activities in the ballfields are ongoing with the ballfields expected to reopen in May. Please note that this schedule is weather dependent.
  • Near Hampden Avenue between Akron and Yosemite streets. Crews continue to work at the regulator station in this area. Work will continue into summer 2021.

Please stay clear of work areas for your safety and the safety of our crews. Please note that construction schedules are subject to change.

Click here to view a map of current and upcoming work areas.


Friday, April 2, 2021

Over the coming weeks, construction activities will take place in the following areas:

  • Cherry Creek State Park
    • Crews continue to install the natural gas line in the Park along Peoria Street, heading toward Belleview Avenue. Construction in Cherry Creek State Park will continue through 2021.
    • A section of the Cottonwood Creek Trail is closed through April. Please follow posted detours and directions from our crews. View a map of the trail closure.
    • Restoration of previous work areas along Peoria Street will begin next week and take place through spring.
  • Village Greens Park east of Cherry Creek Village North. Crews began restoring the baseball fields this week. Restoration activities will happen through April. Please note that this schedule is weather dependent.
  • Near Boston Street and Chester Way north of Mansfield Avenue. Crews will install the natural gas line in the grass median between these streets as early as Monday, April 12.
  • Near Hampden Avenue between Akron and Yosemite streets. Crews continue to work at the regulator station in this area. Work will continue into summer 2021.

Please stay clear of work areas for your safety and the safety of our crews. Please note that construction schedules are subject to change.