Updates

The project is under construction.

Friday, Sept. 17, 2021

We have completed nearly 90% of line installation. We will continue to update you on our progress as we have more news to report.

Over the coming weeks, construction will take place in the following areas:

  • Near Hampden Avenue between Akron and Yosemite streets.
    • Regulator station work through fall.
    • Testing activities in the coming weeks.
  • Near Lehigh Avenue between Boston Street and Chester Way.
    • Final restoration in October.
  • Cherry Creek State Park.
    • Construction through fall.
    • Restoration of previous work areas.
  • Near Havana Street and Berry Avenue.
    • Construction resuming in late October.
  • Near Caley Avenue and Troy Circle.
    • Testing activities in the coming weeks.

Testing activities will cause noise, and you will see equipment and crews.

Please stay clear of work areas for your safety and the safety of our crews. Construction schedules are subject to change.

View a map of current and upcoming work areas.


Friday, Sept. 3, 2021

Crews will not work Saturday, Sept. 4, 2021, through Monday, Sept. 6, 2021, in observance of Labor Day. Construction will resume on Tuesday, Sept. 7, 2021.

Over the coming weeks, construction will take place in the following areas:

  • Cherry Creek State Park.
    • Construction through the end of the year.
    • The Butterfly Hill and Pope trails are open.
    • We continue to restore previous work areas.
  • Near Lehigh Avenue between Boston Street and Chester Way.
    • Final restoration of work areas in the coming months.
  • Near Hampden Avenue between Akron and Yosemite streets.
    • Activities at the regulator station will continue through this fall.

Please stay clear of work areas for your safety and the safety of our crews. Construction schedules are subject to change.

View a map of current and upcoming work areas.


Friday, Aug. 20, 2021

Over the coming weeks, construction will take place in the following areas:

  • Cherry Creek State Park.
    • Construction will continue through the end of the year.
    • We are restoring previous work areas along Peoria Street.
    • Passive prairie dog relocation efforts are ongoing. Please obey trail closures, model airplane rules (including not flying over trails) and directions from our crews.
  • Near Lehigh Avenue between Boston Street and Chester Way.
    • Restoration of work areas in the grass median will begin in the coming weeks.
    • You will see traffic control and detours during restoration. A full closure of Chester Way will be in place.
  • Near Hampden Avenue between Akron and Yosemite streets.
    • Activities at the regulator station will continue through this fall.

Please stay clear of work areas for your safety and the safety of our crews. Please note that construction schedules are subject to change.

View a map of current and upcoming work areas.